      Below is a news article from Swedish Television (SVT) translated to english using LLM. Couldn’t find it in english. Original article

      New Stringent Environmental Requirements Threaten Small Hydropower Plants

      Published on May 10, 2022

      Over a 20-year period, around 1,800 small hydropower plants in Sweden are set to have their conditions re-evaluated by the land and environmental courts to ensure they meet the requirements of the EU’s Water Framework Directive. According to hydropower plant owners, these evaluations entail strict demands and increased costs that threaten the existence of culturally significant small hydropower plants.

      Located along the Alsterån River in Nybro Municipality, one of Magnus Edvinsson’s hydropower plants has been in operation since the 1800s. He, like many other owners of small hydropower plants, is facing upcoming re-evaluations of environmental conditions to determine if they comply with environmental legislation.

      According to Magnus Edvinsson, the measures and court costs could spell the end for many small hydropower plants.

      “We’ve seen costs of 10 million Swedish Kronor for a single small hydropower plant. That completely shatters the economy of a company like this,” he explains.

      Ensuring Fish Passage

      The aim is to establish modern environmental conditions for all watercourses in Sweden. This includes promoting biological diversity, which might involve requirements for fish passages to be built, allowing aquatic organisms to move freely in the waterways.

      The Water Authorities have determined that each water body must achieve good ecological status. According to Magnus Edvinsson, the environmental quality standard imposes excessively high demands and could result in costly reconstruction efforts.

      “In our industry organization, we’ve already received indications that 30 percent of the small hydropower plant owners in the initial review group are considering dismantling their facilities even before the court review takes place. It’s not unlikely that it could reach up to 50 percent choosing to decommission once they are in court. It’s a shocking figure, and this is happening at the same time as we are experiencing the worst energy crisis in modern history,” says Magnus Edvinsson.